Final Account: Lignum Vitae Room
Ref HH-2026-LIG-001
6 September 2026
Project Closing · All Trades Complete · Final Account
Dear Tricia and Karline,
The Lignum Vitae Room is built. Every trade has finished: the electrical rework and ceiling reinstatement, the windows and door, the flooring, the paint and wallpaper, the feature lighting, and the audio-visual fit-out. All furniture has been supplied and delivered. The one task still to be carried out is assembling and installing the conference table and chairs, which HelloHOME has waived and will complete at a time that suits the Club.
This is your final account. It sets out the scope delivered, the final position reconciled line by line against the quote, the concessions applied, and the balance now due. The balance requested here is $1,350,950, which settles every section of works, goods, and materials in full. After that, $437,683 remains on the project, being the professional fee balance and nothing else. One item of work is still outstanding, the installation of the conference table and chairs, and HelloHOME has waived the charge for it. Nothing further will be added to the account.
The room was found to be tied into an already overloaded grid and could not carry the conference table, the AC, and the new lighting on the existing supply. Independent circuitry was run and the electricals reworked back to the breaker, work that sat outside the original scope. On top of that: ceiling and wall lighting installed across ten points, fourteen 110v plug points fitted, smoke detector recessed, switches recessed and updated to decora, waterproof exterior switch replaced, and 3" conduit run for internet and data. Feature lighting comprises the multi-bar pendant over the table, six 100cm linear bar lights, one 120cm linear bar light installed vertically over the sideboard, and the artwork back light over the framing.
Ceiling and walls smoothed with Sure Patch across 775 sq ft, damaged drywall removed and replaced, and drywall cladding installed and finished ready for decoration.
Two aluminium fixed arch windows and two aluminium sliding arch windows fabricated, delivered, and installed. The entry door was refurbished rather than replaced, and fitted with a smart lock, new hinges, an internal sliding lock, and batteries.
425 sq ft of vinyl plank flooring supplied and installed, with 84 running feet of skirting board removed and reinstalled.
Full preparation, priming, and painting throughout. Linen grasscloth wallpaper supplied and hung as the feature wall finish.
Television supplied, delivered, cleared, mounted, and commissioned, with cabling and cable management dressed in.
Conference table supplied and delivered. Fourteen conference chairs supplied and delivered against twelve quoted, at a heavier-duty specification than the one originally priced. Serving buffet built to the custom specification agreed: 72" wide by 24" deep by 32" high, with a 24" open bay, a 30" double-door cabinet, and an 18" drawer bank, finished in the same colours as the conference table. Installation and assembly of the table and chairs remains outstanding and has been waived in full.
Vintage tennis racquets sourced and framed for the room, and full site cleanup and rubble removal carried out on completion.
Installation and assembly of the conference table and chairs has not yet been carried out. It was quoted at $50,000 and HelloHOME has waived it in full, so it is not billed in this account, forms no part of the balance below, and will not be invoiced later. It will be scheduled and completed at your convenience at no charge. All furniture has been supplied, delivered, and paid for. Once the $1,350,950 requested below is settled, the only item left on the project is the professional fee balance of $437,683.
The quote carried a 20% contingency provision of $645,359 against quoted works of $3,226,795. That provision has been fully consumed. Works finished at $4,123,413 net of concessions, $896,618 above the quoted works figure, so the contingency absorbed $645,359 of the movement and $251,259 sits above it. With the professional fee tracking $50,252 higher on the larger works total, the account closes $301,511, or 6.5%, above the agreed quote.
The principal driver was electrical. The room was found to be tied into an already overloaded grid, which meant independent circuitry had to be run and the electricals reworked back to the breaker, work that sat outside the original scope. That, together with the feature lighting specified after the quote and the upgraded conference chairs, is where the contingency went.
Three concessions were granted on this project and are already reflected in every figure in this account. They are set out here in full.
Each section below shows every line as quoted against the final billed figure, net of concessions, with a note on what moved and why. All amounts in JMD.
Click any section to open its line detail.
| Line item | Quoted | Final | +/− |
|---|---|---|---|
| Install lights, ceiling & walls | $32,000 | $80,000 | +$48,000 |
| Independent circuit for conference table, panel box work & AC / lighting reroute | $35,000 | $84,000 | +$49,000 |
| Recess smoke detector | $9,600 | $9,600 | On budget |
| Recess switch & update to decora | $8,000 | $8,000 | On budget |
| Run 3" conduit for internet / data | $16,000 | $16,000 | On budget |
| Install 110v plug points x14 | Not quoted | $112,000 | +$112,000 |
| Change waterproof exterior switch | Not quoted | $8,000 | +$8,000 |
| General material (wire, boxes, conduit, fittings) | $68,380 | $269,150 | +$200,770 |
| Back light over the framing | $105,000 | $41,480 | −$63,520 |
| Feature pendant light over the table | Not quoted | $133,180 | +$133,180 |
| Linear bar lights 100CM x6 | Not quoted | $140,880 | +$140,880 |
| Linear bar light 120CM x1, over the sideboard | Not quoted | $30,390 | +$30,390 |
| Track lights | $90,000 | Not billed | −$90,000 |
| Seven quoted electrical points not required on site | $100,000 | Not billed | −$100,000 |
| Section total | $463,980 | $932,680 | +$468,700 |
| Line item | Quoted | Final | +/− |
|---|---|---|---|
| Sure Patch, smooth ceiling & walls | $100,750 | $100,750 | On budget |
| Remove & replace drywall | $55,755 | $55,755 | On budget |
| Drywall cladding | $46,410 | $46,410 | On budget |
| Material, Quotation 50725 | $85,000 | $85,000 | On budget |
| Section total | $287,915 | $287,915 | On budget |
| Line item | Quoted | Final | +/− |
|---|---|---|---|
| Aluminium fixed arch window x2 | $264,900 | $264,900 | On budget |
| Aluminium sliding arch window a | $115,150 | $115,150 | On budget |
| Aluminium sliding arch window b | $102,300 | $102,300 | On budget |
| Window installation | $48,000 | $48,000 | On budget |
| Transportation | $7,500 | $7,500 | On budget |
| Refurbish entry door | $99,400 | $99,400 | On budget |
| Smart lock | $56,320 | Not billed | −$56,320 |
| Front door hinges | Not quoted | $12,060 | +$12,060 |
| Sliding lock, inside of door | Not quoted | $5,140 | +$5,140 |
| Door lock batteries | Not quoted | $3,730 | +$3,730 |
| Paint samples | Not quoted | $8,000 | +$8,000 |
| Section total | $693,570 | $666,180 | −$27,390 |
| Line item | Quoted | Final | +/− |
|---|---|---|---|
| Vinyl plank material | $233,890 | $233,890 | On budget |
| Vinyl wood flooring installation | $93,500 | $85,000 | −$8,500 |
| Remove & install skirting boards | $22,680 | $22,680 | On budget |
| Cement, floor | Not quoted | $1,850 | +$1,850 |
| Skirting board installation (job-work line) | $49,500 | Not billed | −$49,500 |
| Section total | $399,570 | $343,420 | −$56,150 |
| Line item | Quoted | Final | +/− |
|---|---|---|---|
| Painter labour | $112,500 | $112,500 | On budget |
| Paint | $42,500 | $43,660 | +$1,160 |
| Sandpaper | $3,000 | $3,000 | On budget |
| Section total | $158,000 | $159,160 | +$1,160 |
| Line item | Quoted | Final | +/− |
|---|---|---|---|
| Television, all-in incl. shipping & clearance | $337,250 | $360,000 | +$22,750 |
| Cabling, cable management & TV mount | $65,000 | Not billed | −$65,000 |
| Installation & assembly | $30,000 | Not billed | −$30,000 |
| Section total | $432,250 | $360,000 | −$72,250 |
| Line item | Quoted | Final | +/− |
|---|---|---|---|
| Conference chairs | $181,440 | $511,588 | +$330,148 |
| Conference table | $499,270 | $492,800 | −$6,470 |
| Serving buffet, custom build | $60,800 | $64,950 | +$4,150 |
| Installation & assembly | $50,000 | Not billed | −$50,000 |
| Section total | $791,510 | $1,069,338 | +$277,828 |
| Line item | Quoted | Final | +/− |
|---|---|---|---|
| Site cleanup & rubble removal | Not quoted | $101,550 | +$101,550 |
| Linen grasscloth wallpaper | Not quoted | $88,850 | +$88,850 |
| Framing of vintage racquets | Not quoted | $73,870 | +$73,870 |
| Purchase of vintage tennis racquets | Not quoted | $40,450 | +$40,450 |
| Section total | Not quoted | $304,720 | +$304,720 |
| Date | Ref | Description | Line | Amount | Running Bal. |
|---|---|---|---|---|---|
| 03 Jul | PAY-002 | Electricals - General Material (100% of billed) | L013 | $269,150 | $2,890,313 |
| 10 Jul | PAY-001 | Window & Door - Window labour 50% (Aluminium Fix Window Arch) | L020 | $132,450 | $2,757,863 |
| 10 Jul | PAY-001b | Window & Door - Window labour 50% (Aluminium Slide Window Arch a) | L021 | $57,575 | $2,700,288 |
| 10 Jul | PAY-001c | Window & Door - Window labour 50% (Aluminium Slide Window Arch b) | L022 | $51,150 | $2,649,138 |
| 10 Jul | PAY-001d | Window & Door - Window labour 50% (Installation) | L023 | $24,000 | $2,625,138 |
| 10 Jul | PAY-001e | Window & Door - Window labour 50% (Transportation) | L024 | $3,750 | $2,621,388 |
| 16 Jul | PAY-003 | Electricals - Feature pendant light (100% of billed) | L047 | $133,180 | $2,488,208 |
| 20 Jul | PAY-005 | Electricals - Linear bar light 120CM x1 (100% of billed) | L049 | $30,390 | $2,457,818 |
| 21 Jul | PAY-004 | Electricals - Linear bar lights 100CM x6 (100% of billed) | L048 | $140,880 | $2,316,938 |
| 21 Jul | PAY-006 | Window & Door - Door refurbishment (50% of billed) | L026 | $49,700 | $2,267,238 |
| 21 Jul | PAY-016 | Electronics - Television, all-in incl. shipping & clearance | L038 | $360,000 | $1,907,238 |
| 24 Jul | PAY-013 | Furniture - Conference Table (100% of billed) | L043 | $492,800 | $1,414,438 |
| 24 Jul | PAY-014 | Furniture - Conference Chairs x14 (100% of billed, net of concession) | L044 | $511,588 | $902,850 |
| 28 Jul | PAY-011 | Painting - Paint & sundries, Diamond Paints | L036 | $43,660 | $859,190 |
| 28 Jul | PAY-012 | Painting - Sandpaper | L037 | $3,000 | $856,190 |
| 31 Jul | PAY-007 | Drywall - Sure Patch / ceiling patching (100% of billed) | L016 | $100,750 | $755,440 |
| 31 Jul | PAY-008 | Drywall - Remove & replace / partition (100% of billed) | L017 | $55,755 | $699,685 |
| 31 Jul | PAY-009 | Drywall - Drywall cladding / wall install (100% of billed) | L018 | $46,410 | $653,275 |
| 31 Jul | PAY-015 | Furniture - Serving buffet / sideboard (100% of billed) | L045 | $64,950 | $588,325 |
| 01 Aug | PAY-010 | Painting - Painter labour (50% of billed) | L035 | $56,250 | $532,075 |
| 17 Aug | PAY-018 | Electricals - Independent circuit / panel box work | L008 | $84,000 | $448,075 |
| 17 Aug | PAY-019 | Drywall - Material, Quotation 50725 | L019 | $85,000 | $363,075 |
| 17 Aug | PAY-020 | Window & Door - Window labour final 50% (Aluminium Fix Window Arch) | L020 | $132,450 | $230,625 |
| 17 Aug | PAY-021 | Window & Door - Window labour final 50% (Aluminium Slide Window Arch a) | L021 | $57,575 | $173,050 |
| 17 Aug | PAY-022 | Window & Door - Window labour final 50% (Aluminium Slide Window Arch b) | L022 | $51,150 | $121,900 |
| 17 Aug | PAY-023 | Window & Door - Window labour final 50% (Installation) | L023 | $24,000 | $97,900 |
| 17 Aug | PAY-024 | Window & Door - Window labour final 50% (Transportation) | L024 | $3,750 | $94,150 |
| 17 Aug | PAY-025 | Floor - Vinyl wood flooring installation (100% of billed) | L028 | $85,000 | $9,150 |
| 17 Aug | PAY-026 | Floor - Remove & install skirting boards (100% of billed) | L029 | $22,680 | ($13,530) |
| 17 Aug | PAY-027 | Floor - Vinyl plank material (100% of billed) | L031 | $233,890 | ($247,420) |
| 17 Aug | PAY-028 | Floor - Cement, miscellaneous | L034 | $1,850 | ($249,270) |
| 17 Aug | PAY-029 | Painting - Painter labour final 50% (settles line in full) | L035 | $56,250 | ($305,520) |
| 17 Aug | PAY-030 | Miscellaneous - Vintage tennis racquets | L054 | $40,450 | ($345,970) |
| 17 Aug | PAY-031 | Miscellaneous - Wallpaper, Linen Grasscloth | L055 | $88,850 | ($434,820) |
| 17 Aug | PAY-032 | Miscellaneous - Framing of racquets | L056 | $73,870 | ($508,690) |
| 17 Aug | PAY-033 | Electricals - Install lights, ceiling & walls x10 | L001 | $80,000 | ($588,690) |
| 17 Aug | PAY-034 | Electricals - Recess smoke detector | L002 | $9,600 | ($598,290) |
| 17 Aug | PAY-035 | Electricals - Recess switch & update to decora | L003 | $8,000 | ($606,290) |
| 17 Aug | PAY-036 | Electricals - Conduit for internet / data | L009 | $16,000 | ($622,290) |
| 17 Aug | PAY-037 | Electricals - Change waterproof outside switch | L053 | $8,000 | ($630,290) |
| 17 Aug | PAY-038 | Electricals - Install 110v plug points x14 | L052 | $112,000 | ($742,290) |
| 17 Aug | PAY-039 | Electricals - Back light, over the framing | L015 | $41,480 | ($783,770) |
| 17 Aug | PAY-040 | Window & Door - Smart lock, front door (supplied at no charge) | L027 | $0 | ($783,770) |
| 17 Aug | PAY-041 | Window & Door - Front door hinges | L058 | $12,060 | ($795,830) |
| 17 Aug | PAY-042 | Window & Door - Sliding lock, inside of door | L059 | $5,140 | ($800,970) |
| 17 Aug | PAY-043 | Window & Door - Door lock batteries | L060 | $3,730 | ($804,700) |
| Total billed and settled with suppliers | $3,964,163 | ($804,700) | |||
Every item on this project has been supplied and paid for in full. The balance below settles the outstanding section balances against work already delivered and goods already in the room. The professional fee balance is not included in this request and is set out separately underneath.
Put simply: $1,350,950 now closes out every section of works, goods, and materials. After that the professional fee balance of $437,683 is the only item left on the project. We are glad to walk the room with you and go through any line on this account in person.
Thank you for the confidence the Club placed in HelloHOME. It has been a pleasure bringing the Lignum Vitae Room back, and we would be glad to do it again. Let us know when suits for the table and chairs and we will get it assembled.
Warm regards,
Carou Ralph & Keisha-Maria Cools-Lartigue