Final Account: Lignum Vitae Room
Ref HH-2026-LIG-001
6 September 2026

Project Closing · All Trades Complete · Final Account

The Lignum Vitae Room: All Works Complete, One Item to Install

Dear Tricia and Karline,

The Lignum Vitae Room is built. Every trade has finished: the electrical rework and ceiling reinstatement, the windows and door, the flooring, the paint and wallpaper, the feature lighting, and the audio-visual fit-out. All furniture has been supplied and delivered. The one task still to be carried out is assembling and installing the conference table and chairs, which HelloHOME has waived and will complete at a time that suits the Club.

This is your final account. It sets out the scope delivered, the final position reconciled line by line against the quote, the concessions applied, and the balance now due. The balance requested here is $1,350,950, which settles every section of works, goods, and materials in full. After that, $437,683 remains on the project, being the professional fee balance and nothing else. One item of work is still outstanding, the installation of the conference table and chairs, and HelloHOME has waived the charge for it. Nothing further will be added to the account.

Scope delivered · all trades complete
Electricals: rework, points & feature lighting

The room was found to be tied into an already overloaded grid and could not carry the conference table, the AC, and the new lighting on the existing supply. Independent circuitry was run and the electricals reworked back to the breaker, work that sat outside the original scope. On top of that: ceiling and wall lighting installed across ten points, fourteen 110v plug points fitted, smoke detector recessed, switches recessed and updated to decora, waterproof exterior switch replaced, and 3" conduit run for internet and data. Feature lighting comprises the multi-bar pendant over the table, six 100cm linear bar lights, one 120cm linear bar light installed vertically over the sideboard, and the artwork back light over the framing.

Drywall & ceiling

Ceiling and walls smoothed with Sure Patch across 775 sq ft, damaged drywall removed and replaced, and drywall cladding installed and finished ready for decoration.

Windows & door

Two aluminium fixed arch windows and two aluminium sliding arch windows fabricated, delivered, and installed. The entry door was refurbished rather than replaced, and fitted with a smart lock, new hinges, an internal sliding lock, and batteries.

Floor, skirting & molding

425 sq ft of vinyl plank flooring supplied and installed, with 84 running feet of skirting board removed and reinstalled.

Painting & wall finishes

Full preparation, priming, and painting throughout. Linen grasscloth wallpaper supplied and hung as the feature wall finish.

Electronics

Television supplied, delivered, cleared, mounted, and commissioned, with cabling and cable management dressed in.

Furniture

Conference table supplied and delivered. Fourteen conference chairs supplied and delivered against twelve quoted, at a heavier-duty specification than the one originally priced. Serving buffet built to the custom specification agreed: 72" wide by 24" deep by 32" high, with a 24" open bay, a 30" double-door cabinet, and an 18" drawer bank, finished in the same colours as the conference table. Installation and assembly of the table and chairs remains outstanding and has been waived in full.

Heritage & finishing detail

Vintage tennis racquets sourced and framed for the room, and full site cleanup and rubble removal carried out on completion.

Still to be done · table & chair installation
One item remains open

Installation and assembly of the conference table and chairs has not yet been carried out. It was quoted at $50,000 and HelloHOME has waived it in full, so it is not billed in this account, forms no part of the balance below, and will not be invoiced later. It will be scheduled and completed at your convenience at no charge. All furniture has been supplied, delivered, and paid for. Once the $1,350,950 requested below is settled, the only item left on the project is the professional fee balance of $437,683.

Final financial position · reconciled to completion
Client Financial Summary · Final
Final Project Total*
$4.95M
Concessions Applied
$609,386
Deposit Received
$3.16M
Balance Now Due
$1,350,950
Sections · balance due
BalanceElectricals$275.1K
BalanceDrywall$23.9K
BalanceWindow & Door$347.6K
BalanceFloor, Skirting & Molding$343.4K
BalancePainting$56.2K
Electronics$0
Furniture$0
BalanceMiscellaneous$304.7K
Still to close after this payment
DeferredPM, Design & Contractor Fee$437,683
Table & chair installation$0
Total remaining after this payment$437,683
* Final Project Total of $4,948,096 is the net billed figure across all work, after concessions and reconciled to actual confirmed quantities, against an agreed quote of $4,646,585, and it is the full cost of the project to the Club. All amounts in JMD.
How the contingency was used

The quote carried a 20% contingency provision of $645,359 against quoted works of $3,226,795. That provision has been fully consumed. Works finished at $4,123,413 net of concessions, $896,618 above the quoted works figure, so the contingency absorbed $645,359 of the movement and $251,259 sits above it. With the professional fee tracking $50,252 higher on the larger works total, the account closes $301,511, or 6.5%, above the agreed quote.

The principal driver was electrical. The room was found to be tied into an already overloaded grid, which meant independent circuitry had to be run and the electricals reworked back to the breaker, work that sat outside the original scope. That, together with the feature lighting specified after the quote and the upgraded conference chairs, is where the contingency went.

Quote to final account bridge
Quoted works, before contingency$3,226,795
Final works billed, net of concessions$4,123,413
Movement on works+$896,618
Absorbed by the contingency provision
Contingency provision quoted (20%)$645,359
Provision consumed$645,359 100%
Works movement above the provision$251,259
Professional fee
PM, Design & Contractor Fee, quoted$774,431
PM, Design & Contractor Fee, final$824,683 +$50,252
Final account above agreed quote+$301,511
Agreed quote $4,646,585 → final account $4,948,096. The contingency is not shown as a separate charge on the account; it is carried inside the section figures, which is why every section reads against its own quoted line rather than against a pooled allowance. All amounts in JMD.
Concessions Applied to the Account three goodwill items · click to expand

Three concessions were granted on this project and are already reflected in every figure in this account. They are set out here in full.

1. Conference Chairs Gross $930,160Billed $511,588−$418,572
The chair specified at quote stage was priced at $15,120 a unit for twelve. On review it was not robust enough for a boardroom in daily use, so a considerably heavier-duty chair was substituted at $66,440 a unit, and fourteen were supplied rather than twelve. At list that would have grossed $930,160. HelloHOME absorbed 45% of the line, bringing the billed figure to $511,588, a concession of $418,572.
2. Front Door Smart Lock Quoted $56,320Billed $0−$39,250
The smart lock was supplied and fitted at no charge as a goodwill item. It appears on the payment log at nil so the Club has a complete record of what was installed.
3. Table & Chair Installation Quoted $50,000Billed $0−$50,000
The installation and assembly line is waived in full. The work has not yet been carried out; when it is scheduled, it will be completed at no charge and will not be invoiced.
Gross to net bridge
Gross billing before concessions$5,557,482
Less: line concessions granted−$507,822
Less: professional fee waived on those lines (20%)−$101,564
Total concession value−$609,386
The three concessions carry a value of $609,386, or 11.0% of gross billing. Separately, $95,000 of quoted Electronics work and the $49,500 duplicate skirting installation line were not billed, and the Electricals section returned $190,000 of quoted points and track lights that were not required.
Where the Budget Moved, Line by Line every section, quoted vs final · click to expand

Each section below shows every line as quoted against the final billed figure, net of concessions, with a note on what moved and why. All amounts in JMD.

Click any section to open its line detail.

Electricals Quoted $463,980Final $932,680+$468,700
Line itemQuotedFinal+/−
Install lights, ceiling & walls4 points quoted → 10 installed$32,000$80,000+$48,000
Independent circuit for conference table, panel box work & AC / lighting rerouteroom found on an overloaded grid, reworked back to the breaker, outside original scope$35,000$84,000+$49,000
Recess smoke detector$9,600$9,600On budget
Recess switch & update to decora$8,000$8,000On budget
Run 3" conduit for internet / data$16,000$16,000On budget
Install 110v plug points x14added on siteNot quoted$112,000+$112,000
Change waterproof exterior switchadded on siteNot quoted$8,000+$8,000
General material (wire, boxes, conduit, fittings)tracks the higher point count$68,380$269,150+$200,770
Back light over the framing3 quoted → 1 installed$105,000$41,480−$63,520
Feature pendant light over the tablespecified after the quoteNot quoted$133,180+$133,180
Linear bar lights 100CM x6specified after the quoteNot quoted$140,880+$140,880
Linear bar light 120CM x1, over the sideboardspecified after the quoteNot quoted$30,390+$30,390
Track lights$90,000Not billed−$90,000
Seven quoted electrical points not required on site$100,000Not billed−$100,000
Section total$463,980$932,680+$468,700
Electricals is the largest single movement on the project, and the reason is structural rather than a matter of quantities. The room was found to be tied into an already overloaded grid. It could not carry the conference table, the AC, and the new lighting on the existing supply, so independent circuitry had to be run and the electricals reworked all the way back to the breaker. That work sat outside the original scope entirely; the quote had assumed the existing supply was sound and priced only the points within the room. On top of that the room needed far more points than the walkthrough suggested, and the feature lighting package was specified after the quote was issued. Set against those, the track lights and seven quoted points were dropped, and the back light went from three to one.
Drywall Quoted $287,915Final $287,915On budget
Line itemQuotedFinal+/−
Sure Patch, smooth ceiling & walls775 sq ft$100,750$100,750On budget
Remove & replace drywall94.5 sq ft$55,755$55,755On budget
Drywall cladding119 sq ft$46,410$46,410On budget
Material, Quotation 50725$85,000$85,000On budget
Section total$287,915$287,915On budget
Delivered exactly to quote, line for line.
Window & Door Quoted $693,570Final $666,180−$27,390
Line itemQuotedFinal+/−
Aluminium fixed arch window x2$264,900$264,900On budget
Aluminium sliding arch window a$115,150$115,150On budget
Aluminium sliding arch window b$102,300$102,300On budget
Window installation$48,000$48,000On budget
Transportation$7,500$7,500On budget
Refurbish entry doorrefurbished rather than replaced$99,400$99,400On budget
Smart locksupplied at no charge, full concession$56,320Not billed−$56,320
Front door hingesadded on siteNot quoted$12,060+$12,060
Sliding lock, inside of dooradded on siteNot quoted$5,140+$5,140
Door lock batteriesadded on siteNot quoted$3,730+$3,730
Paint samplesadded on siteNot quoted$8,000+$8,000
Section total$693,570$666,180−$27,390
The windows and door came in exactly as quoted. The section closes under budget because the smart lock, quoted at $56,320, was supplied and fitted free of charge, more than covering the four small items added on site.
Floor, Skirting & Molding Quoted $399,570Final $343,420−$56,150
Line itemQuotedFinal+/−
Vinyl plank material$233,890$233,890On budget
Vinyl wood flooring installation425 sq ft, rate negotiated down$93,500$85,000−$8,500
Remove & install skirting boards84 running ft$22,680$22,680On budget
Cement, flooradded on siteNot quoted$1,850+$1,850
Skirting board installation (job-work line)cancelled, per-foot line used instead$49,500Not billed−$49,500
Section total$399,570$343,420−$56,150
Under budget. The duplicate job-work line for skirting installation was cancelled and the per-foot line used, and the flooring installation rate was negotiated down after the quote.
Painting Quoted $158,000Final $159,160+$1,160
Line itemQuotedFinal+/−
Painter labour$112,500$112,500On budget
Paintactual product cost$42,500$43,660+$1,160
Sandpaper$3,000$3,000On budget
Section total$158,000$159,160+$1,160
Effectively on budget. The only movement is $1,160 on the actual paint cost.
Electronics Quoted $432,250Final $360,000−$72,250
Line itemQuotedFinal+/−
Television, all-in incl. shipping & clearancefinal landed cost$337,250$360,000+$22,750
Cabling, cable management & TV mountnot billed$65,000Not billed−$65,000
Installation & assemblynot billed$30,000Not billed−$30,000
Section total$432,250$360,000−$72,250
Under budget. The television landed $22,750 above the quoted figure once shipping and clearance were settled, but the cabling, mount, and installation lines totalling $95,000 were not billed to the Club.
Furniture Quoted $791,510Final $1,069,338+$277,828
Line itemQuotedFinal+/−
Conference chairs12 quoted at $15,120 each → 14 supplied at $66,440 each; gross $930,160 less 45% concession$181,440$511,588+$330,148
Conference table$499,270$492,800−$6,470
Serving buffet, custom build72" W x 24" D x 32" H to agreed specification$60,800$64,950+$4,150
Installation & assemblygross $50,000, waived in full; work still to be carried out$50,000Not billed−$50,000
Section total$791,510$1,069,338+$277,828
The chairs are the movement here, and they are worth setting out plainly. The chair specified at quote stage was priced at $15,120 a unit. On review it was not robust enough for a boardroom in daily use, so a considerably heavier-duty chair was substituted at $66,440 a unit, and fourteen were supplied rather than the twelve quoted. That would have grossed $930,160. HelloHOME absorbed 45% of it, bringing the billed figure to $511,588. The Club therefore receives fourteen chairs of a materially better specification for $330,148 above the twelve-chair quote, against a gross uplift of $748,720. Installation and assembly of the table and chairs, quoted at $50,000, has been waived in full and will be carried out at no charge.
Miscellaneous Quoted Not quotedFinal $304,720+$304,720
Line itemQuotedFinal+/−
Site cleanup & rubble removalNot quoted$101,550+$101,550
Linen grasscloth wallpaperNot quoted$88,850+$88,850
Framing of vintage racquetsNot quoted$73,870+$73,870
Purchase of vintage tennis racquetsNot quoted$40,450+$40,450
Section totalNot quoted$304,720+$304,720
None of this sat in the original quote. The wallpaper, the racquets, and their framing were added as the room's finishing scheme developed, and the site cleanup was carried out on completion.
Section rollup
Electricals$463,980 → $932,680
Drywall$287,915 → $287,915
Window & Door$693,570 → $666,180
Floor, Skirting & Molding$399,570 → $343,420
Painting$158,000 → $159,160
Electronics$432,250 → $360,000
Furniture$791,510 → $1,069,338
Miscellaneous$0 → $304,720
Contingency provision (20%) consumed in full, carried inside the section figures$645,359 → $0
PM, Design & Contractor Fee$774,431 → $824,683
Final Project Total$4,646,585 → $4,948,096
Payment Log · Full Transaction Detail 46 entries · click to expand
DateRefDescriptionLineAmountRunning Bal.
03 JulPAY-002Electricals - General Material (100% of billed)L013$269,150$2,890,313
10 JulPAY-001Window & Door - Window labour 50% (Aluminium Fix Window Arch)L020$132,450$2,757,863
10 JulPAY-001bWindow & Door - Window labour 50% (Aluminium Slide Window Arch a)L021$57,575$2,700,288
10 JulPAY-001cWindow & Door - Window labour 50% (Aluminium Slide Window Arch b)L022$51,150$2,649,138
10 JulPAY-001dWindow & Door - Window labour 50% (Installation)L023$24,000$2,625,138
10 JulPAY-001eWindow & Door - Window labour 50% (Transportation)L024$3,750$2,621,388
16 JulPAY-003Electricals - Feature pendant light (100% of billed)L047$133,180$2,488,208
20 JulPAY-005Electricals - Linear bar light 120CM x1 (100% of billed)L049$30,390$2,457,818
21 JulPAY-004Electricals - Linear bar lights 100CM x6 (100% of billed)L048$140,880$2,316,938
21 JulPAY-006Window & Door - Door refurbishment (50% of billed)L026$49,700$2,267,238
21 JulPAY-016Electronics - Television, all-in incl. shipping & clearanceL038$360,000$1,907,238
24 JulPAY-013Furniture - Conference Table (100% of billed)L043$492,800$1,414,438
24 JulPAY-014Furniture - Conference Chairs x14 (100% of billed, net of concession)L044$511,588$902,850
28 JulPAY-011Painting - Paint & sundries, Diamond PaintsL036$43,660$859,190
28 JulPAY-012Painting - SandpaperL037$3,000$856,190
31 JulPAY-007Drywall - Sure Patch / ceiling patching (100% of billed)L016$100,750$755,440
31 JulPAY-008Drywall - Remove & replace / partition (100% of billed)L017$55,755$699,685
31 JulPAY-009Drywall - Drywall cladding / wall install (100% of billed)L018$46,410$653,275
31 JulPAY-015Furniture - Serving buffet / sideboard (100% of billed)L045$64,950$588,325
01 AugPAY-010Painting - Painter labour (50% of billed)L035$56,250$532,075
17 AugPAY-018Electricals - Independent circuit / panel box workL008$84,000$448,075
17 AugPAY-019Drywall - Material, Quotation 50725L019$85,000$363,075
17 AugPAY-020Window & Door - Window labour final 50% (Aluminium Fix Window Arch)L020$132,450$230,625
17 AugPAY-021Window & Door - Window labour final 50% (Aluminium Slide Window Arch a)L021$57,575$173,050
17 AugPAY-022Window & Door - Window labour final 50% (Aluminium Slide Window Arch b)L022$51,150$121,900
17 AugPAY-023Window & Door - Window labour final 50% (Installation)L023$24,000$97,900
17 AugPAY-024Window & Door - Window labour final 50% (Transportation)L024$3,750$94,150
17 AugPAY-025Floor - Vinyl wood flooring installation (100% of billed)L028$85,000$9,150
17 AugPAY-026Floor - Remove & install skirting boards (100% of billed)L029$22,680($13,530)
17 AugPAY-027Floor - Vinyl plank material (100% of billed)L031$233,890($247,420)
17 AugPAY-028Floor - Cement, miscellaneousL034$1,850($249,270)
17 AugPAY-029Painting - Painter labour final 50% (settles line in full)L035$56,250($305,520)
17 AugPAY-030Miscellaneous - Vintage tennis racquetsL054$40,450($345,970)
17 AugPAY-031Miscellaneous - Wallpaper, Linen GrassclothL055$88,850($434,820)
17 AugPAY-032Miscellaneous - Framing of racquetsL056$73,870($508,690)
17 AugPAY-033Electricals - Install lights, ceiling & walls x10L001$80,000($588,690)
17 AugPAY-034Electricals - Recess smoke detectorL002$9,600($598,290)
17 AugPAY-035Electricals - Recess switch & update to decoraL003$8,000($606,290)
17 AugPAY-036Electricals - Conduit for internet / dataL009$16,000($622,290)
17 AugPAY-037Electricals - Change waterproof outside switchL053$8,000($630,290)
17 AugPAY-038Electricals - Install 110v plug points x14L052$112,000($742,290)
17 AugPAY-039Electricals - Back light, over the framingL015$41,480($783,770)
17 AugPAY-040Window & Door - Smart lock, front door (supplied at no charge)L027$0($783,770)
17 AugPAY-041Window & Door - Front door hingesL058$12,060($795,830)
17 AugPAY-042Window & Door - Sliding lock, inside of doorL059$5,140($800,970)
17 AugPAY-043Window & Door - Door lock batteriesL060$3,730($804,700)
Total billed and settled with suppliers $3,964,163 ($804,700)
46 transactions logged across July and August 2026, totalling $3,964,163 of items billed and settled with suppliers. The running balance draws down from the $3,159,463 deposit. The closing ($804,700) is the value of goods and works HelloHOME carried and paid for beyond the deposit to keep the trades moving without interruption; it is recovered through the balance requested below. All amounts in JMD.
Balance now due

Every item on this project has been supplied and paid for in full. The balance below settles the outstanding section balances against work already delivered and goods already in the room. The professional fee balance is not included in this request and is set out separately underneath.

Outstanding section balances
Electricals$275,080
Drywall$23,925
Window & Door$347,555
Floor, Skirting & Molding$343,420
Painting$56,250
Miscellaneous wallpaper, racquets & framing, site cleanup$304,720
Electronics settled in full$0
Furniture settled in full$0
Total Now Due $1,350,950
Reconciliation: final account $4,948,096 less deposit received $3,159,463 = $1,788,633. Of that, $1,350,950 is requested here and $437,683 is the deferred professional fee balance. All amounts in JMD.
JMD $1,350,950
What remains after this payment
PM, Design & Contractor Fee, outstanding balance$437,683
Table & chair installation quoted at $50,000, waived in full, no charge to the Club$0
Total Remaining to Close the Project $437,683
Once the $1,350,950 above is settled, $437,683 is all that will be left on this project, and it will be settled on a schedule agreed with the Club. The table and chair installation is still to be carried out and will be done at no charge. Nothing further will be added to the account. All amounts in JMD.

Put simply: $1,350,950 now closes out every section of works, goods, and materials. After that the professional fee balance of $437,683 is the only item left on the project. We are glad to walk the room with you and go through any line on this account in person.

Thank you for the confidence the Club placed in HelloHOME. It has been a pleasure bringing the Lignum Vitae Room back, and we would be glad to do it again. Let us know when suits for the table and chairs and we will get it assembled.

Warm regards,
Carou Ralph & Keisha-Maria Cools-Lartigue